Yenir sand base. Laying concrete mixture in the structure. A. arrays and separate foundations

USSR STATE CONSTRUCTION COMMITTEE

GOSSTROY USSR

SINGLE RATES AND PRICES FOR CONSTRUCTION, INSTALLATION AND REPAIR AND CONSTRUCTION WORKS

COLLECTION E4

INSTALLATION OF PREFACED AND DEVICE OF MONOLITHIC REINFORCED CONCRETE STRUCTURES

ISSUE 1 BUILDINGS AND INDUSTRIAL STRUCTURES

Moscow 1987

Approved by the Decree of the State Construction Committee of the USSR, the State Committee of the USSR on Labor and Social Affairs and the Secretariat of the All-Union Central Council of Trade Unions of December 5, 1986 No. 43/512/29-50 for mandatory use in construction, installation and repair and construction work.

ENiR. Collection E4. Installation of prefabricated and device monolithic reinforced concrete structures. Issue. 1. Buildings and industrial facilities / Gosstroy of the USSR. - M.: Stroyizdat, 1987.

Designed for use in construction and installation, repair and construction and equivalent organizations, as well as in subdivisions (teams, sites) of production associations, enterprises, organizations and institutions engaged in construction and overhaul in an economic way, transferred to new conditions for remuneration of workers in accordance with the resolution of the Central Committee of the CPSU, the Council of Ministers

USSR and the All-Union Central Council of Trade Unions "On the improvement of the organization wages and the introduction of new tariff rates and official salaries for workers in the production sectors of the national economy.

Developed by the Center for Scientific Organization of Labor and Production Management of the USSR Ministry of Tyazhstroy * with the participation of the head NIS Glavkrasnoyarskstroy (section I) and the branch of the Central Non-profit Center in Alma-Ata (section II) using regulatory materials from other ministries and departments under methodological guidance and with the participation of the Central Bureau of Labor Standards in Construction (CBNTS) at the VNIPI Labor in Construction Gosstroy

* Since August 1986, the Ministry of Construction in the regions of the Urals and Western Siberia of the USSR.

The technology for the production of works provided for in the Collection has been agreed with the Central Research and Design and Experimental Institute for Organization, Mechanization and Technical Assistance to Construction (TsNIIOMTP).

Lead performer - K.F. Yarkov (TsNOT and UP).

Performers - M.A. Kuznetsova, N.A. Yakovleva (TsNOT and UP), Ph.D. tech. Sci. Sh.L. Machabeli (TsNIIOMTP), V.I. Petruneva (TsNOT and UP), Ph.D. tech. Sciences B.V. Zhadanovsky (TsNIIOMTP), L.V. Bialik (CBNTS).

Responsible for the release - A.I. Alekseev (TsBNTS).

INTRODUCTION .............................................................. ................................................. ...............................................

SECTION I. INSTALLATION OF PRECORATED CONCRETE STRUCTURES.................................................................................. ......

§ E4-1-1. Installation of foundation blocks or slabs .............................................. ...............................

§ E4-1-2. Installation of grillages and pile heads ....................................................... ....................................

§ E4-1-3. Installation of wall blocks .......................................................... ................................................. .....

§ E4-1-4. Installation of columns and capitals .............................................................. ................................................. .

Enlarged assembly of trusses .............................................. .................................................

Installation of crossbars, purlins, beams and trusses .............................................. ...............................

Laying of floor slabs and coatings .............................................. ................................................

Installation of wall panels, partitions, parapet and eaves plates ..............................................

§ E4-1-9. Installing the screen panels and laying the plates of the canopies of the entrances and support posts ..............................

§ E4-1-10. Installation flights of stairs or laying slabs of landings ..............................

§ E4-1-11. Installation of stair railings............................................................... ......................................

§ E4-1-12. Installation of elements of balconies and loggias .............................................. ...............................

§ E4-1-13. Installation of reinforced concrete volumetric blocks of buildings .............................................. .........

§ E4-1-14. Installation of sanitary units, ventilation units and pipes

garbage chutes .................................................. ................................................. .................

§ E4-1-15. Installation of three-dimensional blocks of elevator shafts .............................................. .........................

§ E4-1-16. Installation of tank wall panels .............................................................. ...............................................

§ E4-1-17 Installation of reinforced concrete window blocks ............................................. ...............................

§ E4-1-18. Installation of sanitary cabins .............................................. ...............................

§ E4-1-19. Arrangement of fences made of prefabricated reinforced concrete elements .......................................................

§ E4-1-20. Laying of reinforced concrete trays .............................................. .........................................

§ E4-1-21. Installing support pads .............................................................. ................................................. ..

§ E4-1-22. Anti-corrosion coating of welded joints............................................................. .............

§ E4-1-23. Fastening external and internal wall panels metal staples....

§ E4-1-24. Fixing gypsum concrete partitions with staples and needles.................................................................. ..

§ E4-1-25. Sealing of structural joints .............................................................. ..................................................

§ E4-1-26. Filling joints of wall panels and floor slabs and coatings .............................................. ....

§ E4-1-27. Insulation and sealing of butt and expansion joints ..............................................................

§ E4-1-28. Caulking, caulking and jointing .............................................................. .................................

§ E4-1-29. Installation of a cement underlay under wall blocks..................................................................

§ E4-1-30. Seal holes in hollow core slabs ah overlaps .............................................. ..........

§ E4-1-31. Blocking mounting holes or openings up to 0.5 m3 .......................

§ E4-1-32. Installation of partition walls drywall sheets on a metal frame..............

SECTION II. DEVICE OF MONOLITHIC CONCRETE AND REINFORCED CONCRETE STRUCTURES. 33

CHAPTER 1. FORMWORKING .............................................................. ...............................................

Technical part................................................ ................................................. .........................

§ E4-1-33. Arrangement of scaffolding supporting formwork .............................................................. ....................

§ E4-1-34. Installation and dismantling of wooden and wood-metal formwork ..............................................

§ E4-1-35. Arrangement and dismantling of suspended formwork for slabs .............................................................. .....

§ E4-1-36. Installation and dismantling of the formwork of the walls of tanks and bunkers ..............................................

§ E4-1-37. Installation and dismantling of metal formwork .......................................................... ....................

§ E4-1-38. Installation and removal of metal block-climbing formwork ..............................................

§ E4-1-39. Arrangement and dismantling of wooden panel formwork of the walls of underground channels....

§ E4-1-40. Enlarged assembly of wood-metal formwork panels and disassembly of enlarged

shields ................................................. ................................................. ...................................

§ E4-1-41. Installation and dismantling of wooden plugs in concrete and reinforced concrete structures45

§ E4-1-42. Installation of steel embedded parts in the formwork .......................................................... ..............

§ E4-1-43. Miscellaneous formwork .................................................................. ..................................................

CHAPTER 2. REINFORCEMENT WORKS .............................................................. ...............................................

§ E4-1-44. Installation of reinforcing meshes and frames .............................................. ...............................

§ E4-1-45. Laying of reinforcing mesh by the method of continuous rolling of a roll ..............................................

§ E4-1-46. Installation and tying of reinforcement with individual rods .............................................. ...........

CHAPTER 3. CONCRETE WORKS.................................................................. ................................................. ...

§ E4-1-47. Preparation of concrete mix in stand-alone concrete mixers ..............................................

§ E4-1-48. Supply of concrete mix by concrete pumps .............................................................. ...............................

§ E4-1-49. Laying concrete mixture in the structure .............................................................. ................................

§ E4-1-50. Installation and removal of panels and electrodes for electrical heating of concrete ..............................................

§ E4-1-51. Concrete pouring under equipment .............................................................. .........................

§ E4-1-52. Ironing of concrete surfaces .............................................................. ....................................

§ E4-1-53. Laying the concrete mixture in individual structures manually ..............................................................

§ E4-1-54. Miscellaneous concrete work .................................................................. ................................................. ......

§ E4-1-55. Drilling holes in reinforced concrete structures using a machine with diamond

annular drills ................................................................ ................................................. .........

INTRODUCTION

1. The release standards provide for the installation of prefabricated reinforced concrete and concrete structures, as well as monolithic concrete and reinforced concrete works for civil and industrial buildings and structures.

2. The norms provide for the performance of work in accordance with the permissible deviations taken into account by SNiP III-15-76, SNiP III-16-80, as well as in accordance with the safety requirements in construction SNiP III-4-80.

Workers must know and comply with the requirements provided for by the collection of norms, the above SNiPs, ensuring the required quality of work. Workers must know and follow the safety rules when performing work.

3. The norms of this issue provide for the performance of work at a height of up to 15 m, from the level of planning marks. When performing work at the height of St. 15m, N.W. and Rass. multiply by the following coefficients depending on the height:

up to 20m .... 1.05 (HF-1) "30m .... 1.1 (HF-2)" 40m .... 1.2 (HF-3) over. 40m…1.3 (HF-4)

4. The norms of the relevant paragraphs provide for the installation, rearrangement and removal of inventory scaffolds, ladders, ladders, tables, cradles with a mass of St. 50 kg by crane, and weighing up to 50 kg by hand.

5. Signaling to the driver in cases where the installation of structures is carried out outside the field of view of the crane driver in the absence of means of communication is carried out by an additionally allocated worker and is paid by the time for the time actually worked at the rate of the worker 3 razr.

6. The norms of those paragraphs that take into account the tack, its implementation is provided for by an electric welder of manual welding or a structural assembler who has a second profession of an electric welder.

7. The release standards do not provide for geodetic work.

8. The performance of welding work is not provided for by the norms of release (except for the specified cases) and is additionally normalized according to the norms of Sat. E22 "Welding", no. 1 "Structures of buildings and industrial facilities".

9. The tariffication of the main works was carried out according to the ETKS of works and professions of workers, vol. 3, sec. "Construction, installation and repair and construction work", approved on July 17, 1985, and other works are charged according to the relevant issues and sections of the ETKS.

SECTION I. INSTALLATION OF PRECORATED CONCRETE STRUCTURES Technical part

1. The norms of section I provide for the installation of structures using cranes: tower, crawler and gantry. When performing work with pneumatic wheel cranes and automobile cranes N.vr. and Rass. multiply by 1.1(PM-1), and during the installation of structures using masts equipped with electric winches- by 1.3 (PM-2).

2. The norms provide for the control of cranes by machinists of the 6th category.

When erecting structures by cranes, for whose drivers higher tariff rates are set or by controlled drivers of other categories, if their use is provided for by the PPR, the prices of the drivers should be recalculated at the appropriate tariff rates.

3. The norms of the section, with the exception of cases specifically specified in the paragraphs, take into account and are not separately paid for: slinging and slinging, fastening and removing braces, stretching the mooring, marking installation sites and applying axial marks to structures, bending mounting loops, inspection and cleaning of structures, their places installations and embedded parts from dirt and mortar splashes, reception (during supply and rearrangement) of bunkers and boxes with concrete or mortar mixture, shoveling the finished mortar, signaling during installation.

4. The norms, with the exception of cases specifically stipulated in the paragraphs, take into account the movement of structures, materials and mounting devices by a crane in the area of ​​its operation, the lifting of parts, materials weighing up to 50 kg at a distance of up to 30 m.

5. For brevity, the assemblers for the installation of steel and reinforced concrete structures provided for by the composition of the links are called structural assemblers, the manual welding electric welder is called an electric welder, and the crane operator (crane operator) is called a crane operator.

§ E4-1-1. Installation of foundation blocks or slabs

Guidelines for the application of standards

The norms provide for the installation of tape or free-standing foundation blocks or slabs on a bed of finished cement mortar or ready-made gravel (sand) preparation with checking the base marks on the sights.

The installation of lighthouse blocks of the strip foundation and corner blocks of separate foundations is provided for by the level.

To install ordinary blocks of a strip foundation, a mooring is stretched, ordinary blocks of separate foundations are installed along a stretched axial wire.

Composition of the work

1. Preparation of a bed from a mortar or partial leveling of a finished gravel (sand) base.

2. Installation of foundation blocks (slabs).

3. Checking the correct installation of blocks (plates).

4. Sealing of seams with mortar between the block of strip and composite foundations.

The composition of the link

Table 1

Profession and rank of workers

Foundation blocks or

Foundation blocks

slabs weighing up to 8 tons

soy st. 8t

Structural assembler 5 size.

Crane operator

Norms of time and prices for 1 element

table 2

Foundation

Type of blocks

Mass of blocks

(slabs) t, up to

installers

machinist

structures

Tape (Fig. 1)

a) trapezoidal

Under columns (Fig. 2):

a) whole

Foundation

Type of blocks

Mass of blocks

(slabs) t, up to

installers

machinist

structures

b) glass

c) composite from-

individual elements

Note. When laying composite foundations from trapezoidal blocks, slabs and glass (Fig. 2) under the columns N.vr. and Rass. lines 1 - 4, 11-12 multiply by 1.15 (PR-1).

§ E4-1-2. Installation of grillage and pile caps Guidelines for the application of standards

The norms provide for the installation on previously leveled piles of single and twin heads or grillages on mounting clamps or bedding.

Installation of detachable metal clamps according to the marks is carried out manually with fixing them on piles with coupling bolts.

When installing grillages on clamps, the arrangement of a supporting deck with transverse sawing of timber, followed by their disassembly and storage, was taken into account.

When installing grillages supported by backfilling, the norms take into account the cutting of the soil and the backfilling of slag, crushed stone or sand with a layer of 30-35 cm with manual compaction.

Scope of work

When installing and removing mounting clamps

1. Installation of collars on piles. 2. Alignment of installed clamps with fastening. 3. Covering the upper shelf of the clamps with a ready-made emulsion. 4. Unfastening and removing clamps with storage.

When installing heads and grillages

1. Installation of heads or grillages on piles. 2. Arrangement of a supporting deck with subsequent disassembly. 3. Soil cutting. 4. Filling device with compaction. 5. Alignment of the position of the installed element.

The composition of the link

Table 1

Profession and rank of workers

When installing and

When installing the headband

When installing height-

removing clamps

Structural assembler 4 size.

Crane driver 6 years

table 2

Norms of time and prices for meters indicated in the table

Weight

Name of works

cops, t,

Meter

installers

machinist

structures

Installation of collars on piles and removal

Installation of single heads on

1 cap

one pile or twin heads

Weight

Name of works

cops, t,

Meter

installers

machinist

structures

on two piles supported by clamps

Installation of ro-blocks

sverka on two piles with

relying on

bedding

Note. The work indicated on line No. 3a is normalized jointly according to the norm of line No. 1a, hence the full N.vr. for the installation of a grillage block on two piles with a description for two clamps, it will be:

§ E4-1-3. Installation of wall blocks Instructions for the application of standards

The norms provide for the installation of outdoor and internal walls basements, walls of the above-ground part of buildings, basement and cornice blocks on a bed from a ready-made solution 20-30 mm thick with laying ready-made lighthouses from a solution, ready-made wooden wedges with a mooring tension.

When installing blocks of basement and basement walls, it is planned to fill horizontal and vertical joints with ready-made mortar from both sides of the wall, and in the outer walls of the above-ground part of buildings - only from the inside.

Filling the internal vertical joints between the blocks is done by manually pouring them from above with ready-made concrete mix or mortar.

The norms provide for the installation of anchors for fixing cornice blocks.

Composition of the work

1. Making a bed from a ready-made solution with laying beacons and wedges. 2. Installation of blocks. 3. Reconciliation of installed blocks. 4. Installation of anchors (for cornice blocks). 5. Filling the channels at the joints of the blocks with a concrete mixture or mortar. 6. Filling horizontal and vertical joints with mortar, removing the wedges.

Table 1

Profession and rank of workers

For all designs

Basement wall blocks

except basement walls

Structural assembler 5 size.

Crane operator

A. BLOCK EXTERIOR AND INTERIOR BASEMENT WALLS

table 2

Mass of blocks, t, up to

constructor installers

machinist

Mass of blocks, t, up to

constructor installers

machinist

B. GROUND BLOCKS AND EXTERIOR WALL BLOCKS

Table 3

Time limits and prices for 1 block

Mass of blocks, t,

installers con-

machinist

structures

Basement blocks

Outdoor blocks

ordinary, pro-

wall, pe-

strap,

window sills and

angular and semi-

front-line and

bay windows

B. INTERIOR WALL BLOCKS AND CURTAIN BLOCKS

Table 4

Time limits and prices for 1 block

Mass of blocks

installers con-

machinist

structures

Blocks of internal

ordinary and peremy-

canal

Eaves blocks

straight with offset

corner with offset

straight with offset

corner with offset

Notes:1. In case of floor-by-floor fastening of wall blocks to floor slabs with ready-made forgings, take N.vr. for 1 m of the perimeter of the building. 0.1 man-hour construction assembler 3 categories, Rass. 0-07 (PR-1).

2. The norms provide for the installation of wall blocks with closed joints. When installing wall blocks

with open joints for embedding with bricks 1 m of the joint take N.vr. 0.12 man-h with the composition of the link of concrete workers 4

res. - 1, 3 bits. - 1, Rass. 0-09.5 (PR-2).

§ E4-1-4. Installation of columns and capitals

Guidelines for the application of standards

The norms provide for the installation of one- and two-branch columns in foundation glasses, single-branch columns on lower columns or foundation slabs and the installation of column capitals.

When installing columns in foundation cups, the bottom of the cup is cleaned and, if necessary, the bottom of the cup is leveled with a ready-made mortar.

Temporary fixing and alignment of the position of the columns is provided for using one

night or group conductors, braces, struts, finished metal or wooden wedges.

Installation, removal and rearrangement of single or group conductors are taken into account by the crane.

When installing the capitals on the columns, temporary fastening of the capitals with metal sliding supports is provided.

Scope of work

A. WHEN INSTALLING COLUMNS IN FOUNDATION GLASSES

With the help of conductors

1, Leveling the bottom of the glasses (as needed) with rinsing and cleaning the glass. 2. Installation and fixing of single conductors. 3. Installation of columns. 4. Alignment and temporary fixing of columns in the conductor 5. Separation, removal and rearrangement of conductors. 6. Cleaning conductors from the influx of concrete mixture.

Without the help of conductors

1. Leveling the bottom of the glasses (as needed) with rinsing and cleaning the glass. 2. Installation of columns. 3. Reconciliation and temporary fixing. 4. Removal of temporary fastening (braces).

B. WHEN INSTALLING COLUMNS ON SUBJECT COLUMNS (COLUMN EXTENSIONS) OR FOUNDATION PLATES

With the help of conductors

1. Installation of a single or group conductor with alignment and fixing it. 2. Installation of columns with temporary fixing with the conductor's mounting devices. 3. Reconciliation of the position of the columns. 4. Disconnection of assembly devices of a group conductor or disconnection, removal and rearrangement of a single conductor.

Without the help of conductors

1. Installation of columns. 2. Reconciliation and temporary fixing. 3. Removing the temporary mount.

When installing capitals

1. Installing the capitals of the columns. 2. Reconciliation and temporary fixing. 3. Removal of temporary fastening.

The composition of the link

Table 1

Profession and rank of workers

Mass column installation

Installation of columns weighing from

1 to 20 t and capitals

Structural assembler 5 size.

Crane operator

A. COLUMNS INSTALLED IN FOUNDATION GLASSES

table 2

With the help of conductors

Without the help of conductors

Mass of columns

installers con-

machinist

installers

machinist

structures

structures

With the help of conductors

Without the help of conductors

Mass of columns

installers con-

machinist

installers

machinist

structures

structures

B. COLUMNS. MOUNTED ON SUBSTRATED COLUMNS (COLUMN EXTENSIONS) OR FOUNDATION PLATES

Table 3

Norms of time and prices for 1 column

With the help of conductors

Without the help of conductors

Name

Weight co-

lonn, t, up

installers

machinist

installers

machinist

structures

structures

Columns without ka-

Columns with capi-

Note. The norms for the installation of columns with the help of conductors provide for the operation of a crane serving an integrated team or two links of structural erectors. In cases where the crane serves one link of structural assemblers, N.vr. and Rass. for the crane driver, multiply by 2 with the execution of the relevant act (PR-1).

USSR STATE CONSTRUCTION COMMITTEE
GOSSTROY USSR

UNIFIED RATES AND PRICES
FOR CONSTRUCTION, INSTALLATION
AND REPAIR AND CONSTRUCTION WORKS

COLLECTION E4

ASSEMBLY ASSEMBLY
AND DEVICE OF MONOLITHIC
REINFORCED CONCRETE
STRUCTURES

BRIDGES AND PIPES

DEVELOPED by the All-Union Design and Technological Institute of Transport Construction (VPTItransstroy of the Ministry of Transport Construction) under the methodological guidance and with the participation of the Central Bureau of Labor Standards in Construction (TsBNTS) at the All-Union Research Institute of Labor in Construction of the Gosstroy of the USSR.

APPROVED by the Decree of the State Construction Committee of the USSR, the State Committee of the USSR on Labor and Social Affairs and the Secretariat of the All-Union Central Council of Trade Unions of December 5, 1986 No. 43/512/29-50 for mandatory use in construction, installation and repair and construction work.

The technology for the production of works, provided for in the Collection, is agreed with the technological department of VPTItransstroy.

Introductory part. 6

Technical part. 7

Section I Foundations and supports of bridges. 7

Chapter 1 7

Technical part. 7

§ E4-3-1. The device for crushed stone preparation in the pit. 7

§E4-3-2. Installation of foundation slabs. eight

§ E4-3-3. Installation of foundation blocks. eight

§ E4-3-4. Monolithic joints and seams between foundation slabs or blocks. eleven

§ E4-3-5. Reinforced concrete fencing of support pits. 12

§ E4-3-6. The device of prefabricated grillages. thirteen

§ E4-3-7. Laying the concrete mixture under water using the vertically moved pipe method.. 14

§ E4-3-8. Installation and dismantling of foundation formwork. sixteen

§ E4-3-9. Reinforcement of foundations with meshes and frames. 17

§ E4-3-10. Reinforcement of foundations with rods. 17

§ E4-3-11. Foundation concreting. 17

Chapter 2 eighteen

Technical part. eighteen

§ E4-3-12. Installation of supports from contour blocks. eighteen

§ E4-3-13. Installation of supports from universal blocks ZNIIS.. 19

§ E4-3-14. Installation of filling blocks. 20

§ E4-3-15. Installation of support racks. 21

§ E4-3-16. Installation of support frames. 21

§ E4-3-17. Installation of spacers between frames. 22

§ E4-3-18. Installing shell sections. 23

§ E4-3-19. Reinforcement of joints of shell sections. 24

§ E4-3-20. Installation of crossbar blocks. 25

§ E4-3-21. Installation of a transitional underframe. 25

§ E4-3-22. Installation of elements of the upper part of the abutment. 25

§ E4-3-23. Welding works during monolithic support elements. 26

§ E4-3-24. Monolithing of racks and frames with under-columns. 26

§ E4-3-25. Monolithic support elements. 27

§ E4-3-26. Installation and tension of vertical beams. 28

§ E4-3-27. Laying concrete mixture in prefabricated structures of supports. 29

§ E4-3-28. Caulking and jointing of the seams of the support blocks. thirty

§E4-3-29. The device of inventory suspended scaffolds in the construction of prefabricated and prefabricated monolithic supports. thirty

§ E4-3-30. Pole drain device. 31

§ E4-3-31. Paint waterproofing device. 31

Chapter 3. Construction of columnar supports in frozen and rocky soils. 32

Technical part. 32

§ E4-3-32. Installation of reinforced concrete pillars. 32

§ E4-3-33. The device of monolithic nozzles. 33

Chapter 4 34

Technical part. 34

§ E4-3-34. Arrangement of wooden formwork supports. 35

§ E4-3-35. Installation and removal of steel column formwork. 36

§ E4-3-36. The device and dismantling of the wooden formwork of the crossbar. 36

§ E4-3-37. Installation of reinforcing cages. 37

§ E4-3-38. Pole concreting. 38

§ E4-3-39. The device of massive cladding of supports made of granite stone. 39

§ E4-3-40. Concrete block cladding. 40

Chapter 5 40

Technical part. 40

§ E4-3-41. Assembly and disassembly of sliding formwork. 41

§ E4-3-42. Assembly of sliding formwork lifting devices. 42

§ E4-3-43. Disassembly of sliding formwork lifting devices. 43

§ E4-3-44. Hanging scaffolding. 43

§ E4-3-45. Assembling the crane-mast.. 44

§ E4-3-46. Reinforcement and concreting of supports. 44

Chapter 6 46

Technical part. 46

§ E4-3-47. Installation of foundation blocks. 46

§ E4-3-48. Installation of racks of single-column supports. 47

§ E4-3-49. Installation of stairway support blocks. 47

§ E4-3-50. Installation of beams under the stringer. 48

§ E4-3-51. Installation of stringers. 48

§ E4-3-52. Installation and monolithic spacers. 49

§ E4-3-53. Installation of steps and stair slabs. fifty

§ E4-3-54. Installation of metal railings. fifty

Chapter 7. Construction of tunnel-type overpasses. 51

Technical part. 51

§ E4-3-55. Installation of foundation slabs. 51

§ E4-3-56. Installation of trough-shaped blocks. 52

§ E4-3-57. Installation of retaining wall blocks. 52

§ E4-3-58. Monolithing blocks and foundation slabs. 53

§ E4-3-59. Thermoplastic waterproofing device. 54

Section IISpan structures of bridges. 54

Chapter 8 54

Technical part. 54

§ E4-3-60. Installation of blocks on the stand. 54

§ E4-3-61. Monolithic joints between blocks. 55

§ E4-3-62. Installation of beams. 56

§ E4-3-63. Compression of dry joints. 57

§ E4-3-64. Preparation of epoxy glue. 58

§ E4-3-65. Applying epoxy to blocks. 58

§ E4-3-66. Beam tension. 58

§ E4-3-67. channel injection. 59

§ E4-3-68. Coating anchors with mortar.. 59

§ E4-3-69. Finishing the ends of the beams. 60

§ E4-3-70. Installing and removing ducts. 60

§ E4-3-71. Cleaning seams from glue. 60

Chapter 9 61

Technical part. 61

§ E4-3-72. Installation of steel base plates. 61

§ E4-3-73. Installation of rubber bearings. 61

§ E4-3-74. Arrangement and disassembly of rolling tracks. 61

§ E4-3-75. Transverse movement of beams from the curb to the axis of the track. 62

§ E4-3-76. Installing the beams on the supports with a cantilever crane GEPK-130. 63

§ E4-3-77. Installation of beams on supports with a GEK-80 jib crane. 64

§ E4-3-78. Installation of beams on supports with jib cranes. 65

§ E4-3-79. Installation of beams on supports with console-sluice cranes. 67

§ E4-3-80. Installation of beams on supports with gantry cranes. 68

§ E4-3-81. Installation of hollow core slabs on supports with T-75 trailer cranes. 69

§ E4-3-82. Transverse movement of beams on supports. 69

§ E4-3-83. Installation of beams on the supporting parts with jacks. 70

Chapter 10 70

Technical part. 70

§ E4-3-84. Monolithic longitudinal seams beam slabs. 71

§ E4-3-85. Monolithic longitudinal joints of beam slabs. 72

§ E4-3-86. Monolithic beam diaphragms. 74

Chapter 11 75

Technical part. 75

§ E4-3-87. Unloading and moving blocks. 75

§ E4-3-88. Installation of rubber-fluoroplastic bearing parts. 76

§ E4-3-89. Installation of reinforced concrete pedestals. 77

§ E4-3-90. Installation of support blocks. 77

§ E4-3-91. Installation of blocks weighing up to 20 tons 78

§ E4-3-92. Installation of blocks weighing up to 50 tons by crane SPK-65. 79

§ E4-3-93. Installation of blocks weighing up to 50 tons by crane MSSHK 2´60. 79

§ E4-3-94. Installation of blocks weighing up to 60 tons with a gantry crane .. 80

§ E4-3-95. Joint formwork device. 81

§ E4-3-96. Joint concreting. 81

§ E4-3-97. Applying epoxy to blocks. 82

§ E4-3-98. Installation and tension of mounting bundles for crimping adhesive joints. 82

§ E4-3-99. Compression of the supra-supporting assembly with mounting beams. 83

§ E4-3-100. Installation of the overhead node in the design position. 84

§ E4-3-101. Laying beams in open channels.. 84

§ E4-3-102. Rope laying. 85

§ E4-3-103. Installation of reinforcing bundles in closed channels.. 86

§ E4-3-104. Tension of reinforcing beams. 88

§ E4-3-105. Rope tension. 89

§ E4-3-106. Monolithic bundles and ropes. 90

§ E4-3-107. Injection of block channels. 90

§ E4-3-108. Mounting and dismantling of the steel suspended formwork of the monolithic closing section. 91

§ E4-3-109. Inventory scaffolding. 92

Chapter 12 93

Technical part. 93

§ E4-3-110. Installation of elements of the carriageway of bridges and overpasses. 93

§ E4-3-111. Installation of prefabricated railings for bridges and overpasses. 94

§ E4-3-112. Waterproofing device. 95

§ E4-3-113. Arrangement of the carriageway of road bridges without pasting waterproofing.97

Chapter 13 97

§ E4-3-114. The device of crane ways. 97

§ E4-3-115. Moving cranes at hinged mounting. 98

§ E4-3-116. Movement of the MSSHK 2´60 crane during the installation of superstructures. 99

§ E4-3-117. Connection of portal cranes. 102

§ E4-3-118. Assembly of the crane MKSH-40. 102

§ E4-3-119. Dismantling of the crane MKSH-40. 103

§ E4-3-120. Moving crane MKSH-40. 104

§ E4-3-121. Moving crane MKSH-100. 106

§ E4-3-122. Moving crane LSHK-90. 108

§ E4-3-123. Installation of rail cranes on outriggers. 110

§ E4-3-124. Installation on outrigers of pneumowheel and automobile cranes. 110

Chapter 14. Loading, unloading and transportation of beams and blocks. 111

Technical part. 111

§ E4-3-125. Loading and unloading blocks of supports. 111

§ E4-3-126. Loading and unloading blocks of composite beams of superstructures. 112

§ E4-3-127. Loading and unloading beams of superstructures. 112

§ E4-3-128. Loading and unloading of sidewalk, curb and other blocks. 113

§ E4-3-129. Loading blocks on the platform. 114

§ E4-3-130. Transportation of blocks and beams of superstructures. 114

Section III Manufacture of reinforced concrete structures at landfills. 115

Technical part. 115

Chapter 15 115

§ E4-3-131. Fabrication of loopless beams on a machine designed by Blinkov. 115

§ E4-3-132. Formation on beams of frame-rod anchors of the MIIT system. 116

§ E4-3-133. Transfer of reinforcing beams. 116

§ E4-3-134. Preparation of six-wire coils. 117

§ E4-3-135. Production of bundles from six-wire blanks. 117

§ E4-3-136. Production of bundles from individual wires. 118

§ E4-3-137. Installation of end anchors on bundles. 119

§ E4-3-138. Landing anchor heads on the wires of the bundle. 120

§ E4-3-139. Winding bundles on a drum. 120

§ E4-3-140. Production of bundles from seven-wire twisted strands. 120

Chapter 16 121

Technical part. 121

§ E4-3-141. Tension of loopless reinforcing beams. 121

§ E4-3-142. Assembly of reinforcing cages of beams. 123

§ E4-3-143. Reinforcement of beams and blocks with individual rods. 124

§ E4-3-144. Installation of reinforcing cages. 124

§ E4-3-145. Formwork assembly and disassembly. 125

§ E4-3-146. Formwork cleaning and lubrication. 126

§ E4-3-147. Concreting of beams and blocks of superstructures. 127

§ E4-3-148. Transfer of tensile force with emphasis on concrete. 127

§ E4-3-149. Removing blocks from the stand. 127

Chapter 17 128

Technical part. 128

§ E4-3-150. Assembly of reinforcing cages of the block. 128

§ E4-3-151. Installation of embedded parts in the frame of the block. 128

§ E4-3-152. Installation of reinforcing cages in the formwork. 129

§ E4-3-153. Installing and removing ducts. 130

§ E4-3-154. Formwork assembly and disassembly. 131

§ E4-3-155. Separation of blocks. 132

§ E4-3-156. Removing blocks from the stand. 133

Chapter 18 133

Technical part. 133

§ E4-3-157. Formwork assembly and disassembly. 133

§ E4-3-158. Reinforcement of plates with individual rods. 135

§ E4-3-159. Installation of formwork with reinforcing cage in the curing chamber. 136

§ E4-3-160. Slab concreting. 136

§ E4-3-161. Removing slabs from the steaming chamber.. 136

§ E4-3-162. Assembly of reinforcing cages of blocks. 137

§ E4-3-163. Assembly and disassembly of wooden formwork. 138

§ E4-3-164. Block concreting. 138

§ E4-3-165. Block storage. 138

Chapter 19 139

§ E4-3-166. Assembly of reinforcing cages from individual rods. 139

§ E4-3-167. Installation of reinforcing cages in the formwork. 139

§ E4-3-168. Formwork assembly and disassembly. 140

§ E4-3-169. Concreting of support structures. 144

§ E4-3-170. Extraction of structures from the steaming chamber.. 145

§ E4-3-171. Various works.. 146

Section IVCulverts. 146

Technical part. 146

Chapter 20 147

§ E4-3-172. Preparation device. 147

§ E4-3-173. Filling the preparation with cement mortar.. 148

§ E4-3-174. Installation of foundation blocks and slabs. 148

Chapter 21 149

§ E4-3-175. Feeding and sorting pipe elements at the construction site. 149

§ E4-3-176. Installation of head blocks. 150

§ E4-3-177. Device concrete pad. 151

§ E4-3-178. Link installation round pipes. 151

§ E4-3-179. Installation of sections of rectangular pipes. 152

§ E4-3-180. Assembly of concrete pipes. 152

§ E4-3-181. Monolithic seams. 153

§ E4-3-182. Sealing and waterproofing of link seams. 154

When installing floors without an interlayer

1. Installation of lighthouse rails or frames. 2. Preparation of cement milk or PVAD and priming the screed with it. 3. Laying the finished mosaic mortar with leveling and compaction. 4. Removing rails or frames. 5. Filling the joints with ready-made mosaic mortar.

When installing floors with rammed crumbs, add:

scattering the crumbs on the floor surface and ramming the crumbs into the solution layer.

When installing floors with veins, add:

marking the pattern with laying veins, straightening brass and copper veins if necessary.

When arranging floors using marble breccias, add:

sorting breccias by color and size, laying marble breccias.

The composition of the link

Facing-mosaic 4 size. - one

" " 2 " - 1

Norms of time and prices for 1 m 2 of floor and 1 m of veins

floors

Veins

Type of floors

with interlayer device

without interlayer device

glass

brass or copper

Solid (seamless)

0,93

0-66,5

0,58

0-41,5

0,04

0-02,9

0,07

0-05

With a straight pattern up to 3 m of veins per 1 m 2 of the floor or with a checkered pattern

1,1

0-78,7

0,67

0-47,9

0,09

0-06,4

0,13

0-09,3

With a rectilinear pattern of more than 3 m of veins per 1 m 2 of the floor or with a curvilinear pattern

1,4

1-00

0,83

0-59,3

0,18

0-12,9

0,19

0-13,6

Notes: 1. When installing floors with tamping crumbs N. vr. and Rust. gr. "a" and "b" multiply by 1.2 (PR-1).

2. N. vr. and Rust. it is planned to install floors from one or two mortars of different color or decorative filling. When constructing floors from solutions of three or more colors, N. time. and Rust. gr. "a" and "b" of lines 2 and 3 are multiplied by 1.2 (PR-2).

3. When constructing floors using marble breccias N. vr. and Rust. gr. "a" and "b" multiplied by 1.2 (PR-3).

4. In solid floors (line 1), the laying of veins (line 1, columns "c" and "d") is provided only when installing a frieze.

5. Preparation of terrazzo mortar should be standardized and paid additionally according to § E19-53.

§ E19-30. MOSAIC (TERRAZZA) FLOORS

Scope of work

When grinding

1. Coarse grinding of the floor surface with wetting and sanding. 2. Grinding the floor surface with wetting and sanding. 3. Puttying the surface with cement mortar. 4. Removing putty. 5. Cleaning and washing of the coating. 6. Change of grinding stones.

When polishing

1. Wetting the surface with water. 2. Partial filling. 3. Removing putty with fine-grained abrasives and washing off the sludge. 4. Polishing.

FOR GRINDING AND POLISHING COATINGS

Table 1

Norms of time and prices for 1 m 2 of the floor and for 1 m of skirting boards or fillets

Surface type

Finishing method

Productivity of grinding machines and aggregates, m 2 / h

Composition of workers

grinding

Powder polishing

floors

Mechanized

4-6

Mosaic tiler

4 bits

0,32

0-25,3

0,56

7,5

Too

0,27

0-21,3

0-44,2

up to 20

"

0,23

0-18,2

0,56

0-44,2

30-40

Mosaic tiler

4 bits

0,17

0-13,4

3a

55-60

"

0,04

0-03,2

Manual

Mosaic tiler

3 bits

1,7

1-19

2,6

1-82

Skirting boards or fillets

Mechanized (by machine IE-8201A)

The same, 6 bits.

0,44

0-46,6

Manual

The same, 5 times.

0,58

0-52,8

1,4

1-27

Notes: 1. When grinding mosaic floors with veins, N. vr. and Rust. multiply by 1.1 (PR-1).

2. The production necessity of performing work manually and their volume are documented by an act approved by the work foreman.

WHEN FINISHING PLACES OF CONNECTIONS OF FLOORS TO WALLS AND COLUMNS

table 2

Norms of time and prices for 1 m of junction

Type of finish

finishing method,

car brand

Composition of working mosaic tilers

N. vr.

Rass.

grinding

Mechanized

I-54

4 bits

0,14

0-11,1

Sanding and polishing

IE-8201A

Too

0,36

0-28,4

grinding

Manual

3 bits

0,27

0-18,9

Powder polishing

Too

0,46

0-32,2

Note. N. vr. and Rust. grinding and polishing of junctions with a strip width of up to 120 mm is provided.

§ E19-31. ARRANGEMENT OF CONCRETE FLOORS

WITHOUT THE USE OF A VACUUM UNIT

Composition of the work

1. Wetting the base with water. 2. Installation of lighthouse rails. 3. Laying ready-mixed concrete with leveling. 4. Compaction of the concrete mixture with a surface vibrator or a vibrating screed. 5. Smoothing and careful leveling concrete surface rail. 6. Removal of lighthouse rails and sealing of the remaining furrows. 7. Smoothing the surface with metal trowels. 8. Grouting the coating surface with a machine.

Table 1

Name of works

The composition of the link of concrete workers

N. vr.

Rass.

Floor arrangement

4 bits - one

2 " - 1

9,6

6-86

Including grouting the coating surface by machine

4 bits - one

3,3

2-61

Notes: 1. N. time. and Rust. tab. 1 provides for a coating thickness of 20-30 mm.

2. N. vr. and Rust. tab. 1 provides for the installation of floors in rooms with an area of ​​St. 20 m2. When installing floors in rooms up to 20 m 2 N. vr. and Rust. multiply by 1.25 (PR-1).

WITH VACUUM UNIT

Composition of the work

1. Wetting the base with water. 2. Installation of lighthouse rails. 3. Reception and laying of the finished concrete mix with leveling. 4. Compaction of the concrete mixture with a platform vibrator or a vibrating screed. 5. Leveling the concrete surface. 6. Laying filter cloths and suction mat. 7. Vacuuming. 8. Removal, cleaning and rinsing of filter cloths and suction mat. 9. Removal, cleaning of lighthouse rails and sealing of the remaining furrows. 10. Smoothing with disk machines. 11. Grouting with paddle machines.

table 2

2 floors

The composition of the link

Layer thickness, mm

100

up to 150

up to 200

up to 250

Vacuum unit driver 5 years.

9,5

8-65

10,5

9-56

11

10-01

12

10-92

concrete workers

4 bits - one

3 " - 1

2 " - 1

29,5

20-95

32,5

23-08

35

24-85

38

26-98

§ E19-32. INSTALLATION OF CEMENT FLOORS

WHEN LAYING THE SOLUTION BY HAND

Composition of the work

1. Surface wetting concrete base water. 2. Installation of lighthouse rails on the finished underlying layer. 3. Laying, leveling and compacting the cement-sand mortar. 4. Removal of lighthouse rails and filling of furrows. 5. Smoothing the surface of the coating with metal trowels.

Table 1

Norms of time and prices for 100 m 2 of floor

The composition of the link of concrete workers

Layer thickness, mm

Floor area, m 2

N. vr.

Rass.

4 bits - one

To 10

10-65

3 " - 1

St. 10

8-52

2 " - 1

30-40

To 10

12-78

St. 10

9-94

WHEN APPLYING THE SOLUTION WITH A SOLUTION PUMP

Composition of the work

1. Wetting the surface of the concrete base with water. 2. Installation of beacons. 3. Applying mortar to the concrete base using a mortar pump. 4. Leveling and compaction of the solution. 5. Removal of lighthouse rails and filling of furrows. 6. Smoothing the surface of the coating. 7. Carrying hoses during operation. 8. Eliminate blockages in hoses and flush them.

table 2

Norms of time and prices for 100 m 2 of floor

The composition of the link

concrete workers

floor area,

m 2

Productivity of the mortar pump, m 3 / h, up to

4 bits - one

3 " - 1

To 10

16

11-36

13

9-23

2 " - 1

up to 40

11,5

8-17

9,3

6-60

St. 40

9,3

6-60

7,5

5-33

Note. N. vr. and Rust. tab. 2 provides for floor thicknesses up to 40 mm.

WHEN APPLYING METAL-CEMENT COATING

Composition of the work

1. Wetting the base with water. 2. Installation of lighthouse rails. 3. Laying the metal-cement mixture. 4. Leveling and compaction of the metal-cement mixture with a layer of 15-20 mm. 5. Smoothing the surface of the coating. 6. Removing lighthouse rails. 7. Seal of furrows with a metal-cement mixture.

Table 3

Norm of time and price per 100 m 2 of floor

The composition of the link of concrete workers

N. vr.

Rass.

4 bits - one

3 " - 1

26-08

§ E19-33. ASPHALT CONCRETE FLOORS

Composition of the work

1. Installation of lighthouse rails. 2. Laying the asphalt mix. 3. Leveling the mixture. 4. Consolidation of the mixture. 5. Removal of lighthouse rails and filling of furrows. 6. Sprinkling the surface with sand and grouting with a rake.

The composition of the link

Asphalt concrete worker 4 size - one

" 2 " - 1

Norms of time and prices for 100 m 2 of floor

Sealing method

Coating thickness, mm

Hand rollers and rolls

14

10-01

18

12-87

22

15-73

Note. When priming a concrete base with hot bitumen or tar for asphalt concrete workers 3 razr. add to 100 m 2 floor N. vr. 3 man-hours, Rust. 2-10 (PR-1).

Chapter 5. POLYMER FLOORS

§ E19-34. DEVICE OF SINGLE-LAYER PLASTIC

POLYMER CEMENT FLOORS

Guidelines for the application of standards

The norm provides for the installation of coatings from polymer-cement plastic mixtures laid manually. The preparation of a polymer-cement mixture is not taken into account by the norm and is additionally standardized.

Composition of the work

1. Priming the base with an aqueous solution of PVA emulsion with a brush. 2. Installation of beacons. 3. Application and leveling of the polymer-cement mixture. 4. Removal of beacons. 5. Filling the furrows with a mixture with leveling. 6. Grinding the surface with a grinder. 7. Cleaning the floor with water wetting.

Norm of time and price per 1 m 2 of the floor

Note. When installing floors in rooms up to 10 m 2 N. vr. and Rust. multiply by 1.2 (PR-1).

§ E19-35. INSTALLATION OF POLYVINYL ACETATE FLOORS

Characteristics of the conditions for the production of work

The norms provide for the installation of self-leveling mastic floor coverings at an air temperature at floor level of at least + 10 ° C. To protect against mastic pollution, the walls are protected with paper to a height of 50-70 cm. Before applying the mastic, the base is dedusted.

The leveling layer of the coating is applied with mastic with a mobility of 120-140 seconds, and the front layer - 100-120 seconds. The mastic is applied with a spray rod (in the absence of the latter, you can use a spray rod from the S-562 putty unit) or with a spray gun, the diameter of the nozzle nozzle is 4 mm with mastic mobility of 120-140 sec and 6 mm - with 100-120 sec.

Mastic is applied in strips 1.5 m wide from the wall opposite the entrance to the room. The next layer of mastic is applied only after the previous one has hardened. The thickness of the applied layer of 1-1.5 mm each is systematically checked with a metal ruler.

During a break in work, the layer of mastic coating (front or leveling) is reduced "to nothing" and then joined "overlap" (15-20 cm) with the applied subsequent layer of the same composition.

After completion of work and during breaks, containers, tools, mechanisms, hoses, fixtures, taps, valves and plugs are washed with water.

Composition of the work

1. Laying paper at the junction of the floor to the walls (with mechanized application of mastic). 2. The device of the leveling layer. 3. Application of the front layer of mastic.

Norms of time and prices for 100 m 2 of floor

Application method

mastics

The composition of the cladding link synthetic materials

N. vr.

Rass.

fishing rod nozzle

4 bits - one

3 " - 1

2 " - 1

7,8

5-54

Manually

Same

12-78

Chapter 6. MISCELLANEOUS WORKS

Technical part

1. The norms and prices §§ E19-36, E19-38, E19-39, E19-43, E19-45 provide for the installation of floors in rooms with a floor area of ​​​​st. 20 m2. When installing floors in rooms with a floor area of ​​​​up to 20 m 2 N. vr. and Rust. multiply by 1.25 (PM-1).

2. The norms and prices of §§ E19-36-E19-39, E19-43, E19-45 provide for the performance of work from materials delivered directly to the workplace.

3. The norms and prices § E19-46, E19-51 provide for the installation of skirting boards, fillets and frames for ventilation grilles made of pine, spruce and fir. When using hardwoods N. time. and Rust. multiply by 1.2 (PM-2), when using larch and birch - by 1.1 (PM-3).

4. The norms and prices of §§ E19-36, E19-37, E19-43, E19-45 provide for the thickness of the underlying layers and screeds in accordance with SNiP.

5. The norms and prices of § E19-42 provide for the installation of prefabricated screeds from particle boards with dimensions in accordance with GOST 10632-77 *.

§ E19-36. DEVICE OF SANDY UNDERLYING LAYER

Composition of the work

1. Reception of sand from transport devices. 2. Installation of beacon pegs or rails. 3. Laying sand. 4. Leveling the surface of the layer, removing beacons.

The composition of the link

N. vr.

Rass.

Concrete worker 3rd category

10,5

7-35

§ E19-37. DEVICE OF SLAG UNDERLYING LAYER

Composition of the work

1. Installation of lighthouse pegs or rails. 2. Laying and leveling the slag. 3. Leveling the slag layer with a lath. 4. Compaction of slag with manual rammers. 5. Removal of beacons.

Norm of time and price per 100 m 2 of the underlying layer

Composition of workers

N. vr.

Rass.

Concrete worker 3rd category

4,7

3-29

§ E19-38. DEVICE OF CONCRETE UNDERLYING LAYER

Composition of the work

1. Installation of lighthouse pegs and rails. 2. Laying concrete mix with leveling. 3. Compaction of the concrete mixture with a surface vibrator, vibrator or tamping. 4. Leveling the concrete surface with a lath. 5. Removal of beacon pegs and rails with sealing of the remaining furrows.

Way

The composition of the link

Layer thickness, mm, up to

seals

concrete workers

100

150

200

250

Surface vibrator or vibrator

3 bits - one

2 " - 1

7,5

5-03

9,6

6-43

11,5

7-71

13,5

9-05

Manually

Too

11,5

7-71

14,5

9-72

17,5

11-73

§ E19-39. DEVICE OF GROUND STONE UNDERLYING LAYER

The norms provide for the installation of an underlying layer without pouring with a solution.

Composition of the work

1. Installation of lighthouse rails. 2. Laying and leveling of crushed stone. 3. Compaction of crushed stone. 4. Checking the thickness of the compacted layer.

Norms of time and prices for 100 m 2 of the underlying layer

The composition of the link

concrete workers

layer thickness,

mm, up to

N. vr.

Rass.

3 bits - one

100

10-05

2 " - 1

150

14-07

§ E19-40. SURFACE PREPARATION

UNDER LOOSE POLYVINYL ACETATE FLOORS

Composition of the work

1. Priming the screed with an aqueous solution of PVA emulsion. 2. Sealing irregularities, cracks, potholes manually with ready-made polyvinyl acetate putty. 3. Grinding and priming of sealed areas, if necessary. 4. Sanding the base. 5. Surface cleaning after grinding.

Norms of time and prices for 100 m 2 of the base of the floor

Way of doing work

The composition of the link cladding synthetic

When applying primer and putty

materials

for 1 time

for 2 times

Priming with a spray gun, puttying with a nozzle rod, sanding with a grinder

4 bits - 2

3 " - 1

2 " - 1

11,5

8-40

20,5

14-97

Priming with a spray gun, puttying with a nozzle rod, other operations - manually

Too

17

12-41

29

21-17

Priming with a spray gun, other operations by hand

4 bits - one

3 " - 1

2 " - 1

19,5

13-85

33

23-43

3

Manually

4 bits - one

3 " - 1

2 " - 1

20,5

14-56

34,5

24-50

4

Including:

Priming the screed with an aqueous solution

spray gun

3 bits

1,5

1-05

2,5

1-75

5

emulsions

manually

Too

2,3

1-61

3,9

2-73

6

Sealing irregularities, cracks and potholes with polyvinyl acetate putty manually

"

0,3

0-21

7

Sanding closed areas

grinder

"

0,14

0-09,8

8

manually

"

0,42

0-29,4

9

Priming of closed places

spray gun

"

0,11

0-07,7

10

manually

"

0,17

0-11,9

11

Surface putty

fishing rod-nozzle

4 bits

2,8

2-21

5,4

4-27

12

grounds

manually

3 bits

5,9

4-13

10

7-00

13

Base grinding

grinder

4 bits

3,2

2-53

5,2

4-11

14

manually

Too

8,4

6-64

13,5

10-67

15

a

b

§ E19-41. PREPARATION OF THE CONCRETE SUBSTRATE

Scope of work

When cleaning the base compressed air with compressor

1. Towing rubber hoses up to 30 m and connecting to the compressor. 2. Blowing out the concrete base from dust and debris with compressed air from the compressor.

When cleaning the base with an electric brush and a vacuum cleaner

1. Sweeping the surface of the base with wetting with water, removing debris from the working area. 2. Cleaning the base with an electric brush D-378 and roughening it. 3. Dedusting the base with a PP-1 vacuum cleaner. 4. Marking the finished floor on the walls using a flexible level and a marking cord.

When washing the base with water

1. Toe up to a distance of 30 m and connect rubber hoses to the water supply. 2. Thorough washing of the concrete base with water from hoses.

Norms of time and prices for 100 m 2 of prepared surface

Name of works

Composition of workers

N. vr.

Rass.

Cleaning the base with compressed air using a compressor

Concrete worker 2nd category

6,7

4-29

1

Cleaning the base with a D-378 electric brush and a PP-1 vacuum cleaner

concrete workers

3 bits - one

2 " - 1

5,7

3-82

2

Flushing the base with water from rubber hoses

Utility

worker - 1 cut.

9,1

5-37

3

§ E19-42. DEVICE OF COUPLES FROM WOOD PLATES

FOR WOOD FIBER BOARD DEVICES

Scope of work

On mastic in one layer

1. Priming of the base. 2. Marking and cutting plates. 3. Application of hot bituminous mastic. 4. Laying wood fiber boards. 5. Cleaning the seams from mastic.

Dry in two coats

1. Marking and cutting plates. 2. Laying wood fiber boards.

Table 1

Norms of time and prices for 100 m 2 screeds

Laying method

Slabs area, m 2 , before

The composition of the parquet unit

N. vr.

Rass.

On mastic

5

3 bits

10,5

7-35

1

Dry

2

Too

6,2

4-34

2

WHEN INSTRUMENT FROM WOODEN BOARDS

Composition of the work

1. Priming of the base. 2. Laying the slabs dry with adjustment in place. 3. Marking and cutting plates with a circular saw. 4. Edge trimming of boards by hand if necessary. 5. Hot application bituminous mastic. 6. Laying tiles. 7. Elimination of sags of laid slabs with a fence.

table 2

Norms of time and prices for 100 m 2 screeds

Name of works

The composition of the parquet unit

N. vr.

Rass.

Slab laying

3 bits

18,5

12-95

1

Sag trimming

hand planer

Too

5

3-50

2

stacked slabs

electric planer

4 bits

3,1

2-45

3

Note. When installing screeds in rooms up to 10 m 2 N. vr. and Rust. multiply by 1.2 (PR-1).

§ E19-43. MANUAL CEMENT SCREED DEVICE

Composition of the work

1. Wetting the base with water. 2. Reception of the solution for the ceiling from the bunker (when installing a screed on a slag base). 3. Installation of lighthouse rails according to the level. 4. Laying, leveling and compacting the mortar with a vibrating screed. 5. Removal of lighthouse rails and filling of furrows. 6. Smoothing the surface by hand.

Norms of time and prices for 100 m 2 screeds

Name of works

The composition of the link of concrete workers

N. vr.

Rass.

Base tie device

concrete

3 bits - 2

2 " - 1

23

15-64

1

slag

18,5

12-58

2

Grouting the surface of the screed trowel up to 50 m 2 /h

4 bits

4,8

3-79

3

§ E19-44. CEMENT SCREED DEVICE

WITH APPLICATION OF SOLUTION WITH A SOLUTION PUMP

Guidelines for the application of standards

The norms provide for the installation of a cement screed on interfloor ceilings under parquet floors from cement mortar 35-40 mm thick along a slag or sand layer with mechanized supply and application of the mortar with a mortar pump with a capacity of 6 m 3 /h

§ E4-1-49. Laying the concrete mixture in the structure

Application note

The norms provide for the reception and placement of the concrete mixture by buckets supplied by a crane, conveyor, concrete pumps and dump trucks directly into the structure to be concreted or along trays (trunks), with partial transfer of the concrete mixture. The laid concrete mixture is leveled and compacted with vibrators. The exposed concrete surface is smoothed out. In the process, trays or trunks are cleaned and rearranged.

Composition of the work

1. Acceptance of concrete mix.
2. Laying the concrete mixture directly at the place of laying or along the trays (trunks).
3. Leveling of the concrete mix with its partial transfer.
4. Compaction of the concrete mixture with vibrators.
5. Smoothing out the exposed surface of concrete.
6. Rearrangement of vibrators, trays or trunks with their cleaning.

The composition of the link

Concrete worker 4 size - one
» 2 » - 1

A. SOLIDAGES AND INDIVIDUAL FOUNDATIONS

Table 1

Concrete supply method N.T. Rass.
Crane in buckets in a structure with a volume, m 3, up to 3 0,42 0-30 1
Cranes in buckets in a design with a volume, m 3, up to 5 0,34 0-24,3 2
Crane in tubs, conveyors, concrete pumps in a structure with a volume, m 3:
before 10 0,33 0-23,6 3
« 25 0,26 0-18,6 4
« 30 0,23 0-16,4 5
St. 30 0,22 0-15,7 6
Dump trucks with a carrying capacity of up to 5 tons (regardless of the volume of construction) 0,34 0-24,3 7

Notes: 1. When laying concrete mix with "raisin" N.v. and Rass. multiply by 1.2 (PR-1), including laying "raisins". The scope of work is taken together with the "raisin".
2. When laying the concrete mixture in densely reinforced foundations, N.v. and Rass. multiply by 1.1 (PR-2), unreinforced - by 0.9 (PR-3).
3. When laying the concrete mixture in arrays as part of the concrete worker's link 4 razr. be replaced by a concrete worker 3 razr., and Rast. recalculate.

B. TAPE FOUNDATIONS AND ELEMENTS OF FRAME STRUCTURES

table 2

Norms of time and prices for 1 m³ of concrete or reinforced concrete in business

Constructions N.T. Rass.
up to 600 0,3 0-21,5 1
Strip foundations width, mm St. 600 0,23 0-16,4 2
Columns and racks of frames at the smallest side up to 300 2,2 1-57 3
cross-section of a column or rack, mm up to 500 1,5 1-07 4
St. 500 1,1 0-78,7 5
Beamless slab column capitals 0,82 0-58,6 6
Beams, purlins and crossbars with a width, mm up to 150 1,4 1-00 7
up to 250 1,1 0-78,7 8
St. 250 0,89 0-63,6 9
Slabs and ribbed floors (including beams and to 10 1,3 0-93 10
runs) with the area between the beams, m 2 up to 20 0,98 0-70,1 11
St. 20 0,81 0-57,9 12
Beamless ceilings with area between axles to 10 0,85 0-60,8 13
columns, m 2 up to 20 0,69 0-49,3 14
St. 20 0,57 0-40,8 15

Notes: 1. When concreting columns and racks of reinforced concrete frames from the side or individual columns in stone buildings N.v. and Rass. lines No. 3-6 multiplied by 1.25 (PR-4).
2. When concreting slabs (except for beamless ones) with double reinforcement N.v. and Rass. lines No. 10-12 multiplied by 1.15 (PR-5).
3. Concreting of floors with a slab located below the beams shall be normalized separately: the slab as beamless coatings - according to lines No. 13-15, and beams - according to lines No. 7-9 of this paragraph.
4. The bottoms of the tanks should be normalized as beamless ceilings (lines No. 13-15).
5. When concreting floors up to 5 m2 in one place, N.v. and Rass. lines No. 10 and 13 multiplied by 1.2 (PR-6).
6. When laying concrete mix with "raisins" in strip foundations N.T. and Rass. lines No. 1 and 2 multiplied by 1.2 (PR-7). The scope of work is taken together with the "raisin".

B. WALLS AND PARTITIONS

Table 3

Norms of time and prices for 1 m³ of concrete or reinforced concrete in business

Constructions Thickness of walls or partitions, mm
up to 100 up to 150 up to 200 up to 300 St. 300
Rectilinear vertical walls or partitions 3,5 2,3 1,6 1,2 0,79 1
Rectilinear inclined and curved tank walls up to 1 5,9 5,4 2
radius, m until 3 4,8 4,1 2,8 1,9 1,4 3
up to 5 4,4 3,3 2,2 1,7 1,2 4
to 10 3,4 2,7 1,9 1,4 0,9 5
St. ten 2,8 2,2 1,5 1,1 0,74 6
Inclined walls of bunkers with a capacity, m 3 to 10 4,4 3,4 2,3 1,7 1,2 7
up to 15 3,6 2,8 1,9 1,4 0,94 8
up to 20 2,9 2,2 1,5 1,1 0,76 9
St. 20 2,3 2 1,2 0,86 0,6 10
a b in G d

Note. The norms provide for concreting walls with single reinforcement. When concreting walls without reinforcement L.v. and Rass. multiply by 0.75 (PR-8), when concreting walls with double reinforcement N.v. and Rass. multiply column "a" and "b" by 1.25 (PR-9), column "c" - "d" - by 1.15 (PR-10).

D. STAIRCASES

Table 4

Norms of time and prices for 1 m³ of concrete or reinforced concrete in business